Wathba Contract Timeframe Clause Overview
📑 5 slides
👁 34 views
📅 3/11/2026
📄 PDF
Contract Review Cycles
15-day review cycle for technical submittals from first submission to final approval
2
Personnel Changes
- 14-day advance notice required for key personnel substitutions
- Owner has 15 days to approve/reject substitute personnel after receipt
- Removal costs for unacceptable personnel borne by Contractor
- Initial personnel names must be submitted within 30 days of contract
3
Dispute Resolution
- 14-day window to file written protest after Owner decision
- 30-day period for Owner to respond to protest before arbitration
- Neutral advisor appointment within 15 days if dispute unresolved
- Arbitration panel formation within 1 month if no neutral selected
4
Change Management
- 14-day response window for Contractor to agree/disagree with changes
- Change proposals must include cost breakdown and delay impact
- 21-day lead time for alternative material/equipment approvals
- Owner evaluation and contract amendment follow proposal submission
5
Completion & Warranty
- 21-day Owner response time for completion certificate requests
- 24-month general warranty period from taking-over certificate
- 60-month absolute cutoff for all warranty obligations
- 30-day cure period for deficiencies before final certificate