Wathba Contract Timeframe Clause Overview

📑 5 slides 👁 34 views 📅 3/11/2026 📄 PDF
0.0 (0 ratings)

Contract Review Cycles

15-day review cycle for technical submittals from first submission to final approval

Contract Review Cycles
2

Personnel Changes

  • 14-day advance notice required for key personnel substitutions
  • Owner has 15 days to approve/reject substitute personnel after receipt
  • Removal costs for unacceptable personnel borne by Contractor
  • Initial personnel names must be submitted within 30 days of contract
Personnel Changes
3

Dispute Resolution

  • 14-day window to file written protest after Owner decision
  • 30-day period for Owner to respond to protest before arbitration
  • Neutral advisor appointment within 15 days if dispute unresolved
  • Arbitration panel formation within 1 month if no neutral selected
Dispute Resolution
4

Change Management

  • 14-day response window for Contractor to agree/disagree with changes
  • Change proposals must include cost breakdown and delay impact
  • 21-day lead time for alternative material/equipment approvals
  • Owner evaluation and contract amendment follow proposal submission
Change Management
5

Completion & Warranty

  • 21-day Owner response time for completion certificate requests
  • 24-month general warranty period from taking-over certificate
  • 60-month absolute cutoff for all warranty obligations
  • 30-day cure period for deficiencies before final certificate
Completion & Warranty
1 / 5