Central Mass Facade Cleaning Strategy

📑 7 slides 👁 20 views 📅 2/5/2026
0.0 (0 ratings)

Central Mass: Facade Scope & Access

Building: G + 5 floors with moderate fins, recesses, and projections affecting cleaning

Central Mass: Facade Scope & Access
2

Routine Glazing Cleaning (2 Days)

  • Scope: Vertical glazing (6,600 sq.m), glass balustrades (300 sq.m), skylight (440 sq.m)
  • Methods: Telescopic poles (G, 1st, 5th) and davit system (2nd-4th)
  • Productivity: ~50 sq.m/worker/hour due to complex facade geometry
  • Manpower: 10 workers for 2 days (16 hours) to clean 7,340 sq.m
Routine Glazing Cleaning (2 Days)
3

Skylight Cleaning Strategy

  • Skylight size: 26m × 17m (440 sq.m) with max 13m cleaning reach
  • Solution: Manual telescopic poles from both sides, no gantry needed
  • Benefits: Reduced O&M, no mechanical systems, better value engineering
  • Eliminates long-term risks of powered equipment maintenance
Skylight Cleaning Strategy
4

BMU & Permanent Anchor Assessment

  • Permanent BMU/anchors rejected due to architectural sensitivity
  • Fifth-floor terrace has luxury/ceremonial importance - minimal visual impact needed
  • Temporary davit system provides controlled access without permanent fixtures
  • Conclusion: Current solution is complete, efficient, and low-impact
BMU & Permanent Anchor Assessment
5

Wing Cleaning Scope & Rates

  • Typical wing: 1,300 sq.m glazing (G+1), 740 sq.m recessed (L2), 740 sq.m skylights
  • Stone cladding: ~3,000 sq.m (mechanically fixed natural stone)
  • Productivity: 60 sq.m/hour (glazing), 40 sq.m/hour (stone)
  • Daily capacity: 8 workers × 8 hours = 64 man-hours/day
Wing Cleaning Scope & Rates
6

Full Facade Deep Cleaning

  • Scope: All glazing (2,780 sq.m/wing) + stone cladding (3,000 sq.m/wing)
  • Duration: ~2 days/wing (121 man-hours), ~4 days for two wings
  • Stone cleaning interval: 12-24 months for mechanically fixed stone
  • No BMU needed: Ground-based systems sufficient for entire facade
Full Facade Deep Cleaning
7

Atrium Cleaning Strategy

  • Features: 2,500 sq.m perforated screens (L2-5), 440 sq.m skylight (28.5m height)
  • Method: Scaffolding for screens (vacuum + brush), detergent for skylight
  • Interval: 18-24 months due to controlled AC environment
  • Duration: ~4 days total (8 workers) including scaffolding setup
Atrium Cleaning Strategy
1 / 7