APWRIMS 2.0 – Sensor Installation Status
📑 10 slides
👁 18 views
📅 2/5/2026
APWRIMS 2.0 – Project Overview
Deployment of IoT sensors for real-time irrigation and water monitoring in KWD.
2
KWD – Sub Divisions Covered
- Duggirala, Repalle, Bapatla, and Chirala are the key sub-divisions.
- Each area has unique irrigation needs and sensor deployment plans.
- Comprehensive coverage ensures efficient water management across KWD.
3
Sensor Allocation – Sub Division Wise
- Duggirala: 33 Level & 33 Soil Moisture Sensors.
- Repalle: 23 Level & 23 Soil Moisture Sensors.
- Bapatla: 20 Level & 20 Soil Moisture Sensors.
- Chirala: 24 Level & 24 Soil Moisture Sensors.
4
Installation Status – Chirala
- 100% installation completed successfully.
- All sensors are operational and transmitting data.
- No pending works or technical issues reported.
5
Installation Status – Bapatla
- 95% installation completed; minor balance works pending.
- Remaining installations are under progress.
- Expected to complete within the target date.
6
Installation Status – Duggirala
- 98% installation completed; final installations in progress.
- Minor civil works pending in a few locations.
- On track for timely completion.
7
Installation Status – Repalle
- Civil works are currently in progress.
- Sensor installations will commence post civil works.
- Dedicated team monitoring progress closely.
8
Overall Project Progress
- Average sensor installation progress: 80%.
- Remaining activities: civil works and final installations.
- No major technical challenges observed.
9
Completion Plan & Target Date
- Civil works and balance installations under close monitoring.
- Dedicated teams deployed at all locations.
- Target completion date: 10-02-2026.
10
Conclusion
- APWRIMS 2.0 progressing systematically in KWD.
- Major installations completed; project on track.
- Expected to meet the committed timeline.